Wednesday, 11 March 2009

Thameslink Programme - Key Output Zero

377501
377501377501
377501377501
377501377501
377501377501

Pictures are of FCC unit 377501 (the first of 23 Electrostars to be deliveried) departing platform four at Blackfriars. The unit was returning to Selhurst before going onto Derby the following day.

As the Thameslink programme is now under way the first major step of the programme is about to begin and is going to have massive affect on the customers using the Thameslink route and also SouthEastern's customers on the services that currently terimate in Blackfriars.

The Thameslink Programme was broken down into three output phases. The first, Key Output Zero hits on the 23rd March. This will see the bays at Blackfriars horded off and the station rebuilt while serving trains. Moorgate will lose its Thameslink branch and Barbican will lose mainline trains and become a London Underground station only. Sevenoaks services will be extended northways with all but 5 services going as far as Kentish Town with some peak working going even futher. The current SouthEastern trains to (AM peak) and from (PM peak) Blackfriars will be extended as far as Bedford.

To achieve this First Capital Connect (FCC) are gaining additional stock to run all these extra services. Now this is where the problems arise. Due to massive problems Bombarbier have had with some suppliers being out of business. This has also affected the London Overground 378s. Because of the fact that now building work has started and the Thameslink Programme can not be put back any futher, a train cascade is now taking place to ensure that FCC can cope with the demands of a Key Output Zero (KO0) timetable. FCC will now recieve eight 377/2 Electrostar (which are actually the same as the 377/5 FCC are waiting to be deliveried). This would mean that Southern are multiple units short. To this end they are getting some 375 Electrostars from SouthEastern, Dual Voltage 350/1s from London Midland and using some 442 EMUs to cover their services.

The bad news is this is now enough units to cover everything so the following services are going to be DC only Networkers services instead of going futher north. All will terimate at City Thameslink.

AM Peak
0740 Sevenoaks to (Kentish Town) City Thameslink
*8 car 319 now 6 car Networker (465 + 466)
0752 Sevenoaks to (Luton) City Thameslink
*8 car 319 now 8 car Networker (465 x2)

PM Peak
1650 (Luton) City Thameslink to Sevenoaks
* 8 car 319 now 8 car Networker (465 x2)
1808 (Kentish Town) City Thameslink to Sevenoaks
* 8 car 319 now 8 car Networker (465 + 466 x2)
1906 Sevenoaks to (Kentish Town) City Thameslink
* 8 car 319 now 8 car Networker (465 x2)

Ther is also an extra train that will start at Farringdon. This is because the unit will be formed of two 4 car 317 units that are AC only so are unable to work south of Farringdon. The units will run the following service

1816 Farringdon to Bedford
St Pancras International 1820, St Albans 1842, Harpenden 1848, Luton Airport Parkway 1854, Luton 1857, Harlington 1905 and arrive at Bedford 1920

The joint SouthEastern/FCC services will including the following as well as the Sevenoaks services. These will use 4 or 8 car 319 trains to achieve this

AM Peak
2 trains from Orpington via Catford
2 trains from Orpington via Herne Hill
2 trains from Bromley South via Catford
1 train from Beckenham Junction via Herne Hill
1 train from Kent House via Herne Hill

PM Peak
1 train to Orpington via Catford
2 trains to Beckenham Junction via Herne Hill

Long distance services will be as follows

AM Peak
0609 Bearstead to Bedford via Maidstone East
0623 Ashford International to Bedford via Maidstone East
0729 Rochester to bedford

PM Peak
1622 Bedford to Gillingham via Herne Hill
1646 Bedford to Bedford via Maidstone East
1700 Bedford to Gillingham via Herne Hill

So the Fleet for FCC Thameslink come KO0 will be as follows

317 x2 (borrowed from FCC Great Northern route)
319 x86 (the whole 319 fleet)
377/2 x8 (Borrowed from Southern)
377/5 x2 (with a futher 21 to be deliveried during 2009)

This leaves a total of 10 peak trains that are four car units which are as follows

AM Peak
0629 Luton to Sevenoaks
0816 Brighton to Bedford

PM Peak
1507 Brighton to Bedford
1534 Sevenoaks to Bedford
1537 Brighton to Bedford
1544 Luton to Sutton
1613 St Albans to Wimbledon
1711 London Bridge to Brighton
1740 Sutton to St Albans
1757 Wimbledon to Luton
1842 London Bridge to Brighton

Once all 23 377/5 Electrostars are deliveried all AM peak services will be of 8 car units and only six 4 car services in the PM peak. Although there is more than planned 4 car services the capacity remains silmar to the planned KO0 timetable.

Friday, 6 March 2009

Moorgate Closure


The end is coming for the short branch from Farringdon to Moorgate for First Capital Connect's Thameslink route. To make way for the new 12 car platforms at Farringdon the two station link will be cut off from the end of peak traffic on the 2oth March 2009.

Current passanger trains are as follows

Morning arrivals

0659 from Bedford
0723 from Luton
0735 from Luton
0743 from Bedford
0751 from Bedford
0755 from Luton
0819 from Luton
0823 from St Albans
0839 from Bedford
0847 from Bedford
0855 from Luton
0911 from Luton
0941 from St Albans

Evening Departures

1635 to Bedford
1710 to Bedford
1720 to St Albans
1724 to Bedford
1744 to Bedford
1804 to Luton
1816 to Bedford
1828 to Bedford
1840 to Bedford
1906 to Bedford

Come the morning of the 23rd March anyone wanting to get to Barbican and Moorgate will have to change at Frringdon for the Underground. As part of a deal any season ticket for two years after the closure is vaild to Moorgate on the Underground at "no extra cost". After this time I assume that you will need a Zone 1 travelcard to get to Moorgate from stations on the Thameslink route.

Monday, 23 February 2009

TLP Month

Thameslink Hard Hat

March 2009 might as well be called Thameslink Programme (TLP) month from all the changes happening with the staged introduction of Key Output Zero (KO0). This basically is when the Moorgate branch closes and trains from Sevenoaks are (re)added into the Thameslink network due to lack of terminating bays at Blackfriars come the end of the month. The key dates are different to the 'official' dates but I have used the actually changes rather than the basic timetable changes as weekend services as you know is non existence at the moment.

27th Febuary 2009

The final time you'll be able to use Blackfriars Tube station until late (IE nov/dec) 2011. This is due to Network Rail (NR) rebuilding the whole station to provide a proper interchange with the Thameslink station and will have step free access. Please not that although they say it closes on the 2nd Febuary there is engineering work that weekend meaning you can't access the station on the 28th Febuary/1st March.

20th March 2009

This is the final day of services into Moorgate from the north Thameslink route before closure to allow Farringdon's platforms to be extended over the branch's junction to cope with the 12 car trains coming from 2012. The final service should be the 1906 to Bedford calling at Farringdon, St Pancras International, St Albans, Harpenden, Luton, Leagrave and Bedford arriving at 2012.

23rd March 2009

Customer living on the Sevenoaks to Blackfriars via Catford line will come under the Thameslink/First Capital Network with all trains running through the Central London Core to at least as far as Kentish Town. The service will be run by 4 car 319s and in the peaks will be extended to as far as Bedford. The current services from Beckenham Junction, Gillingham, Rochester and Ashford International into Blackfrairs will also be a joint effort with First Capital Connect and SouthEastern. The trains are due to be run by dual voltage 377/5 and are planned to be 8 units if enough 377/5's are delivered for this date.

As you can see the next month sees a lot of changes to both First Capital Connect services as well as SouthEastern services from late March. This is all part of providing more seats for customers using these services. There is still a danger that these keys dates are not meet. As of writing we are a 4 weeks away from the latest date and yet we have only had two 377/5's delivered with the first 377501 expected to be in service this week according to the latest dates. The second unit 377504 was delivered last week and has under gone some testing, neither have been on the Thameslink Core as of yet. Something that will have to change very soon. Work on the bridge at Farringdon is also behind but Network rail is stepping up efforts there and beginning to make real effort to meet the deadline. If enough 377's and the bridge at Farringdon isn't ready in time then the whole programme could slip. There is only a few months 'spare' in the time scale before the Olympics hit in 2012. Hopefully FCC, DfT, SouthEastern, NR and Bombardier will have all the problems solved or minimised by the time KO0 kicks in.

Monday, 9 February 2009

Thameslink Programme Update

Just an update on Farringdon works as part of the Thameslink Programme. The first part of the new bridge is finally up and working now. Hoping over the next few weeks the rest of the bridge (to the right of the bit you seen in this picture) will be installed and completed before Moorgate branch is closed and Farringdon gets alot busier interchange.

Also the first of the new trains for First Capital connect is currently on test with the following paths

5Z70 2050 Selhurst depot - London Bridge 2108
5Z70 2114 London Bridge - Gatwick Sidings 2155
5Z71 2208 Gatwick Sidings - London Bridge 2237
5Z72 2245 London Bridge - Brighton 2354
5Z73 0003 Brighton - London Bridge 0055
5Z74 0102 London Bridge - Brighton 0151
5Z75 0200 Brighton - London Bridge 0248
5Z76 0254 London Bridge - Gatwick 0319
5Z77 0325 Gatwick - Selhurst depot

It also seems thats another two 377 (likely 502 and 503) are to be deliveried on saturday morning (if anything like 501 around 0200-0300). This seems to work with the latest information that FCC will run with five 377 in the new timetable on March 22nd.

This is all good news for those affected by the Thameslink programme as it seems things are starting to kick in. I for one can't wait to see what March's timetable change brings us in terms of altered services. So far the information Im getting seems to be that instead of being able to run all but six services as 8 car trains, there will be many more 4 car trains in peak until all 23 377/5 units are in service. To give an idea how long it takes to do a 4 car 377, Im told atleast three cars have been made in jan. This of course is unconfirmed information.

Stay tuned for more updates as events happen including a time line of changes at Blackfriars.